TPO RetroFit over EPDM – Marian Chicago

Ice & Water Shield + Fleece-back TPO RetroFit – St. Paul’s Episcopal
November 15, 2016
TPO RetroFit – Custom Walk Pads – Metal Work
October 19, 2016

TPO RetroFit over EPDM – Marian Chicago

Marian Chicago

Work Performed:

  • Relieved stress in existing EPDM by cutting
  • Built new custom wood nailer to prepare for install of new edge metal
  • Mechanically installed foam board new installation over pre-existing surface
  • Mechanically installed and heat welded new TPO membrane
  • Sumped existing drains into new insulation add on
  • Flashed in all skylights, drains and other projections with TPO pre-formed accessories
  • Installed new walk pad to desired areas via heat welding
  • Custom shop fabricated & installed new 24-ga. metal edge to entire perimeter
  • Performed necessary night-time tie-offs
  • Provided extended warranty from manufacturer and Pinkston-Tadd, Inc.